15 October 2008
The Government of Myanmar has signed an agreement for the development of the Taninthayi hydro power plant, and said that the Yeywa scheme is two-thirds complete.
The Ministry of Electric Power No 1 signed an agreement with two firms, Italian-Thai Development Public Co and Wind Fall Energy Services, to develop the 600MW Taninthayi plant.
The Ministry has also reported that the 790MW Yeywa project on the Myitnge river is almost 66% complete overall, and the RCC dam construction is 96% finished.
Concrete placement for the 134m high dam, which will have a volume of approximately 2.4Mm3, is being done by China's Gezhouba Water and Power. Work began in February 2006 and a year ago more than 60% of the structure had been placed.
Where there's political will, there is a way
政治的な意思がある一方、方法がある
စစ္မွန္တဲ့ခိုင္မာတဲ့နိုင္ငံေရးခံယူခ်က္ရိွရင္ႀကိဳးစားမႈရိွရင္ နိုင္ငံေရးအေျဖ
ထြက္ရပ္လမ္းဟာေသခ်ာေပါက္ရိွတယ္
Burmese Translation-Phone Hlaing-fwubc
စစ္မွန္တဲ့ခိုင္မာတဲ့နိုင္ငံေရးခံယူခ်က္ရိွရင္ႀကိဳးစားမႈရိွရင္ နိုင္ငံေရးအေျဖ
ထြက္ရပ္လမ္းဟာေသခ်ာေပါက္ရိွတယ္
Burmese Translation-Phone Hlaing-fwubc
Thursday, October 16, 2008
Myanmar plans Taninthayi, sees Yeywa two-thirds complete
Subscribe to:
Post Comments (Atom)
0 comments:
Post a Comment